4510452 A09

Bypass has been constructed. It seems like most of the road is built on a overhang over the Selška Sora river. All along the way it is supported by retaining walls. West entrance of the bridge over Selška Sora has been widened. Earthworks and retaining walls were done on the crossroad of old road and new bypass on the western side of Sora river. Multiple adjacent roads were adjusted to the new bypass, so it's definitely worth waiting for an aerial imagery update.

4509508 A09

Both bridges are already standing. Wait for the aerial imagery to update. Bridge is slightly offset to the currently drawn bridge here. Viaduct Jenina has some larger retaining walls to the southeast. Retaining walls were also constructed on southwest side of Visočnik Viaduct. Chapel of St. Joseph is still standing. Traffic portals were also installed on both bridges. On the northern end of Visočnik Vidauct large earthworks are taking place, presumably slip lanes will be constructed there.

4505219

matika

4499315

Tenzor

4499313

Ptuj AP

4508848 A09

note regarding new road: still under construcion, due date unknown. per imagery, car parking will not exist anymore, but the chapel is still standing. road construction also brought huge changes to forested areas and riverbed. a dam is planned to be built nearby. aerial imagery is outdated as bridge is already standing, main road has been moved, and multiple retaining walls and earthworks had been done here. plot once the aerial imagery updates.

4508833 A09

there is another road deviation based off of some imagery, although I'm unsure on the future traffic regime. please wait till the aerial imagery update to confirm further developments of this construction zone.

4508794 A09

per recent construction works, A1 between Fram and Slovenska Bistrica towards Ljubljana will get emergency lanes widened, concrete fence in the middle and multiple soundproof fence sections.
see https://www.instagram.com/p/DBvXhZZOGVp/?img_index=1

4290224 A09

Missing things: Zala river, new protection nets above the river, a road gallery in the third curve coming from Jelični Vrh, one smaller stream

4287479 A09

Please fix scrub area. This area was recently deforestated and should be now made out of two scrub polygons